Fremont Public Schools Bond Issue 

Bond Issue Update

 

Fremont, Neb. – (Dec. 19, 2022)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School / CTE Project Update:

The final construction drawings were completed in November. The final bidding for the project has been completed – Hausmann Construction is working on the project GMP for discussion and approval in January.

 

Washington, Howard, and Clarmar Elementary Project Update: 

Grading, foundation and plumbing rough-in work is in progress at Howard Elementary. Grading and fill is underway at Washington Elementary –  foundations to follow. Site planning at Deer Pointe development is ongoing with City coordination happening for final platting. Site Package bidding package expected in the first part of next year. 

 

Milliken Park Elementary Project Update: 

The interior build-out of the Phase 1 Classrooms and Administration on the west wing is nearing completion. Cabinets, ceilings, lighting, and painting is in progress. Substantial Completion, and the associated design team punchlist for Phase 1, is scheduled for December 20th, 2022. The move from Phase 1 to Phase 2 is being coordinated with FPS Facilities and will take place over the Holiday break.  Construction will extend through December 2023 over multiple phases allowing use of the building during construction.

 

Lenihan Learning Center Project Update: 

Demolition work is nearing completion. Cutting floors and trenching for new underfloor utilities is in progress. Installation of new ductwork and hydronic piping is in progress.  Construction is expected to be complete in July of 2023.

 

Bell Field Elementary Project Update: 

Design work for the Phase 2 interior work will wrap in in December. The project will go out to bid immediately after the holidays, with bids received at the end of January 2023. Interior construction is scheduled to begin in May-June of 2023.

 

Linden Elementary Project Update: 

Design work is in progress in anticipation of Bidding in February-March of 2023. Construction is scheduled to begin in May-June of 2023.

 

Johnson Crossing Academic Center Project Update: 

Design work is in progress in anticipation of Bidding in February-March of 2023. Construction is scheduled to begin in May-June of 2023.

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1duT0t7-8F63gQnfXWk35oVhtHwTkAPOT/view?usp=share_link 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.

Fremont Public Schools Bond Issue 

Bond Issue Update

 

Fremont, Neb. – (Nov. 28, 2022)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School / CTE Project Update:

The geothermal wellfield contractor has completed all the vertical well drilling on-site and is currently tying all the wells together to form the complete system. This scope of work is scheduled to continue through end of this year. The Al Bahe gym bleacher replacement still has an anticipated replacement timeframe of Spring 2023. The final construction drawings have been completed by the design team and the final bidding for the project is currently taking place now through December 1st.

 

Washington, Howard, and Clarmar Elementary Project Update: 

Construction has begun starting with grading and foundations at Howard Elementary. FPS owned properties near Washington Elementary have been demolished with grading and foundations to follow. Playground relocation and geothermal well field work is in the planning phases. Site planning at Deer Pointe Elementary development is ongoing with City coordination happening for final platting. Site package bidding is expected first part of next year. 

 

Milliken Park Elementary Project Update: 

The interior build-out of the Phase 1 Classrooms and Administration offices are nearing completion. Windows have been installed, painting is ready to start. Anticipated completion of Phase 1 construction is December 2, 2022. Construction will extend through December 2023 over multiple phases allowing use of the building during construction.

 

Lenihan Learning Center Project Update: 

Demolition work including ceilings, finishes, and windows is nearly complete. Electrical demolition and evaluation of existing systems is in progress. Shut-down of the existing mechanical system is scheduled for this week.  Construction is expected to be complete in July of 2023.

 

Bell Field Elementary Project Update: 

Design work for the Phase 2 interior work is in progress in anticipation of Bidding in January 2023. Interior construction is scheduled to begin in May-June of 2023.

 

Linden Elementary Project Update: 

Design work is in progress in anticipation of Bidding in January-February of 2023. Construction is scheduled to begin in May-June of 2023.

 

Johnson Crossing Academic Center Project Update: 

Design work is in progress in anticipation of Bidding in January-February of 2023. Construction is scheduled to begin in May-June of 2023.

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1R82ktooJ8bd7fiT93q_hy51Ri46ZDjAr/view?usp=share_link 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.

Fremont Public Schools Bond Issue 

Bond Issue Update

 

Fremont, Neb. – (Oct. 11, 2022)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School / CTE Project Update:

The geothermal wellfield installation work is in progress at the high school and is scheduled to continue through the end of this year. The Al Bahe gym bleacher replacement still has an anticipated replacement timeframe of Spring 2023. Bids for the early site package for various exterior improvements have been received and the scopes of that work are being vetted by Hausmann Construction. The design team will continue to develop the final construction drawings through October. Final bidding for the project will take place in the month of November. Initial exterior site construction is scheduled to commence later this year.

 

Washington, Howard, and Clarmar Elementary Project Update: 

Construction Bid has been approved for the three Elementary Projects. Contracting, preconstruction, and permitting is ongoing. Site Construction expected within the next month. Site planning at Deer Pointe development is ongoing with City of Fremont coordination happening for final platting. Site Package Bidding Package expected first part of next year. 

 

Milliken Park Elementary Project Update:

The interior build-out of the Phase 1 Classrooms and Administration areas continues with rough-ins nearing completion, and wall insulation and gypsum board install starting.  New curbs have been installed for new rooftop mechanical equipment.  New dedicated water service installed for new fire sprinklers.  Construction will extend through December 2023 over multiple phases allowing use of the building during construction.

 

Lenihan Project Update:

DR Anderson started interior demolition of selective ceilings and finishes.  Shop drawing review and material procurement currently in process, including mechanical equipment and exterior storefront windows.  Construction is expected to be complete in July of 2023.

 

Bell Field Elementary Project Update: 

The Phase 1 roof repair project has been completed. Phase 1 project close-out is in progress. Design work for the Phase 2 interior work is in progress in anticipation of Bidding in December 2022 or January 2023. Interior construction is scheduled to begin in May-June of 2023.

 

Linden Elementary Project Update: 

Design work is in progress in anticipation of Bidding in January-February of 2023. Construction is scheduled to begin in May-June of 2023.

 

Johnson Crossing Academic Center Project Update: 

Design work is in progress in anticipation of Bidding in January-February of 2023. Construction is scheduled to begin in May-June of 2023.

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/11NSIqZMejqx4EIrwSApA_DNVKEKmSZSZ/view?usp=sharing 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.

Fremont Public Schools Bond Issue 

Bond Issue Update

 

Fremont, Neb. – (Sep. 16, 2022)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School / CTE Project Update:

The geothermal wellfield installation work is in progress at the high school and is scheduled to continue through fall/early winter of this year. The Al Bahe gym bleacher replacement has an anticipated replacement timeframe of Spring 2023.  An early site package for various exterior improvements has been submitted to Hausmann Construction for bidding at the end of September.  The project team will also be reviewing the updated estimate this month to confirm the anticipated overall project scope and costs for the High School and CTE Facility.  The design team will continue to develop the drawings through October when final construction documents will be completed. Initial exterior site construction is scheduled to commence in November.

 

Washington, Howard, and Clarmar Elementary Project Update: 

The District received bids on September 15th for the construction of the three elementary buildings. General Contractors had the option to bid all 3 new Elementary projects together as one bid or just the Washington site as a single project. The site for the replacement of Clarmar Elementary has been chosen and a purchase agreement has been approved by the Board of Education. The new location for the elementary will be within the Deer Pointe subdivision. 

 

Milliken Park Elementary Project Update: 

Phase 1 Construction is underway. The geothermal well field has been completed. Temporary walls have been constructed at the interior to separate the phase 1 work areas from the rest of the building. The interior build-out of the Phase 1 Classroom and Administration areas, and rough-ins for the Mechanical and Electrical systems are in progress. Construction will extend through December 2023 over multiple phases allowing use of the building during construction.

 

Lenihan Learning Center Project Update: 

DR Anderson Constructors has completed the temporary classroom construction within the existing East Meeting Room space. The District moved the classroom furnishings into the temporary classrooms spaces over the Labor Day weekend. Construction within the existing Lenihan Building commenced on September 6th. Construction is expected to be complete in July of 2023.

 

Bell Field Elementary Project Update: 

The Phase 1 roof repair project will be completed in mid-September 2022. Scope, and Budget verification work is underway in preparation for the Phase 2 interior work. Design work for the Phase 2 interior work will take place during the fall of 2022 for Bidding in December 2022 or January 2023. Interior construction is scheduled to begin in May-June of 2023.

 

Linden Elementary Project Update: 

Scope, and Budget verification work is underway. Design work is starting in August 2022 in anticipation of Bidding in January-February of 2023. Construction is scheduled to begin in May-June of 2023.

 

Johnson Crossing Academic Center Project Update: 

Scope, and Budget verification work is underway. Design work is starting in August 2022 in anticipation of Bidding in January-February of 2023. Construction is scheduled to begin in May-June of 2023.

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1pIDBHRbc9LrzD7FyBvwAZfwCTh-oLCU_/view?usp=sharing 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.

Fremont Public Schools Bond Issue 

Bond Issue Update

 

Fremont, Neb. – (Aug. 16, 2022)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School/CTE Project Update:

The geothermal wellfield installation work is currently underway at the High School and is scheduled to continue through fall of this year. The Al Bahe gym bleacher replacement has an anticipated replacement timeframe of Spring 2023. An early site package for various exterior improvements will be submitted to Hausmann Construction for bidding at the end of August.  The project team will also be reviewing the updated estimate this month to confirm the anticipated overall project scope and costs for the High School and CTE Facility. The design team will continue to develop the drawings through October when final construction documents will be completed and initial exterior site construction is scheduled to commence.

 

Washington, Howard, and Clarmar Elementary Project Update: 

Construction documents are completed and planning to go to bid mid August with a bid date of September 1st. Interested bidders have been contacted. A pre-bid meeting is scheduled for August 17th followed up with a site walk of Washington and Howard to familiarize the bidders with the two sites. 

 

Milliken Park Elementary Project Update: 

Phase 1 Construction is underway. The geothermal well field has been completed. Cheever Construction has created temporary walls at the interior to separate the phase 1 work areas from the rest of the building. The demolition of the existing Classrooms in the phase 1 area has been completed. Interior trenching to accommodate Mechanical and Electrical work for phase 1 have been completed. Construction will extend through December 2023 over multiple phases allowing use of the building during construction.

 

Lenihan Learning Center Project Update: 

The project was bid on July 22nd. A contract with DR Anderson Constructors was approved by the Board of Education on July 26th. A pre-construction meeting was held on-site on August 4th. Ths contractor is proceeding with the construction of temporary classroom space in the Main Street – East Meeting Room. Construction within the Lenihan building will begin in August. The overall project is expected to be complete in July 2023.

 

Bell Field Elementary Project Update: 

Elkhorn West Construction has started work on the Phase 1 roof repair project which will be completed in August 2022. Scope and budget verification work is underway in preparation for the Phase 2 interior work. Design work for the Phase 2 interior work will take place during the fall of 2022 for Bidding in December 2022 or January 2023. Interior construction is scheduled to begin in May-June of 2023.

 

Linden Elementary Project Update: 

Scope, and Budget verification work is underway. Design work is starting in August 2022 in anticipation of Bidding in January-February of 2023. Construction is scheduled to begin in May-June of 2023.

 

Johnson Crossing Academic Center Project Update: 

Scope and budget verification work is underway. Design work is starting in August 2022 in anticipation of Bidding in January-February of 2023. Construction is scheduled to begin in May-June of 2023.

 

The projects continue to develop,” stated Dr. Brad Dahl, associate superintendent. “The volatility in the construction market continues to be a challenge for our team as plans are developed, priced out and ultimately bid.”

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1AJzPy64Ry98BGRVZDJE2zCRKpPjrpg7V/view?usp=sharing 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.

Fremont Public Schools Facility Update 

Bond Issue & Other Projects

 

Fremont, Neb. – (Jul. 15, 2022)  If you have driven through the community this summer you may have noticed some work taking place at several Fremont Public Schools facilities. 

 

Fremont Public Schools continues to move forward with planning and have commenced several projects identified during the $123 million bond issue that was passed by citizens in September 2021. FPS is also working on other exciting projects such as a new track and turfed football field at Fremont Middle School and several Federally funded indoor air quality projects.

 

Milliken Park Elementary Project Update: 

Geothermal Well drilling has started on the City owned ball field and will be completed by early August 2022.  Construction has begun on the interior indoor air quality / safety and security project and will extend through December 2023 over multiple phases.  This project will provide for a relocated office with a secured main entrance and walls / doors in the classrooms for the first time since the building was opened in 1978.  This is an ESSER’s Federal grant funded project.

 

High School/CTE Project Update:

The Geothermal Wellfield work will begin in late July/early August.  A bid package for the replacement of the Al Bahe gym bleachers has been awarded to Carroll Seating. Bleachers will be replaced in the spring of 2023 and completed prior to the fall 2023 sports season. The design team will continue to develop the drawings through October where the final design is still on schedule to be completed. The CTE Center construction is scheduled to be completed in Summer 2024 with the entire High School project completed in Summer 2025.  Hausmann Construction of Lincoln was awarded the Construction Manager contract and continues to solicit pricing from local and regional contractors to complete the work. 

 

Washington, Howard, and Clarmar Elementary Project Update:

Design and coordination of structural, mechanical, electrical and plumbing and architectural systems is ongoing. Detail design work on the interior finishes, casework, and kitchen area is underway. Development of options for the new Clarmar site have been evaluated and are being adjusted with feedback from FPS and the site owner. The three new elementary buildings are scheduled to be completed in Summer 2024.

 

Lenihan Indoor Air Quality Project Update: 

Project bids are due July 22 at 9:00 am and a special Board of Education Meeting is scheduled for July 26 to award a contract.  This is an ESSER’s Federal grant funded project.  Construction is expected to begin in August 2022 and extend into next year, 2023.

 

Bell Field Elementary Project Update: 

The roof repair package bids were received on April 28. Elkhorn West Construction has begun work on the project which will be completed in August. Scope and budget verification work is in progress in preparation for the interior design work to begin in the fall/winter of 2022-23 for bidding in the spring of 2023. Interior construction is scheduled to begin in the summer of 2023.

 

Linden Elementary / Johnson Crossing Academic Center Projects Update: 

Site Survey work has been completed. Design work is scheduled to begin later this month.

 

Fremont Middle School:

A new track and artificial turf football field is being built at the Middle School.  Nemaha Sports Construction is the general contractor.  Sawyer Construction of Fremont is contracted by Nemaha for the site work which began two weeks ago.  Sawyer has been on site and preparing the ground previously occupied by two practice fields for the construction of the new football field and track facility.  This project was identified as a need by the citizens committee and is being funded with non-bond issue District funds.

 

“It’s exciting to see work happening throughout the community,” stated Todd Hansen, Metropolitan Community College executive director, student services and Board of Education Facilities Committee Member.  “A lot of work has gone into the planning leading up to these projects commencing – work continues between the school district and Metropolitan Community College on planning for the new Career Technical Education Center.”

 

“The planning for the new / renovated facilities honoring the three tenets of the bond issue: Improved Learning Environments, Safety and Security improvements and Creating Operational and Energy Efficiencies continues,” shared Jon Ludvigsen, Board of Education Facilities Committee Member. “The students and our community will benefit from these improvements and enhancements for years to come.”

 

As the CTE Center at the High School and the three new elementary replacement building projects are commenced, community ground breaking ceremonies will be planned and announced. 

 

Sandi Proskovec, Board of Education Chair and member of the facilities committee stated, “We appreciate the efforts of those involved to bring the projects and planning to fruition, summer is typically a time to refresh and prepare for the upcoming school year – this year many have been engaged in this important work and their efforts are being recognized.”

 

For more information regarding the FPS facilities improvement projects visit the District’s website at http://fremonttigers.org. 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.

 

Inside Milliken Park
Inside Milliken Park
Milliken Park Geothermal Well drilling
Prepping FHS Track and field for geothermal well drilling
New track at FMS

Fremont Public Schools Bond Issue 

Bond Issue Update

 

Fremont, Neb. – (Jun. 17, 2022)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School/CTE Project Update:

Bids were received for the Geothermal Wellfield scope and were under the original budget. This work has been approved by the Board of Education and work will begin in early July on-site.  A bid package for the replacement of the Al Bahe gym bleachers also will go out to bid over the next couple weeks with an anticipated replacement timeframe of Spring 2023. The project team is also working towards the Design Development submittal which will be submitted to Hausmann Construction in late June who will complete an updated estimate to confirm the anticipated overall project scope for the High School and CTE Center.  The design team will continue to develop the drawings through October where the final design is still on schedule to be completed. The CTE Center construction is scheduled to be completed in Summer 2024.

 

Washington, Howard, and Clarmar Elementary Project Update:

Design and coordination of structural, mechanical, electrical and plumbing and architectural systems is ongoing. Detail design work on the interior finishes, casework, and kitchen area is underway. Development of options for the new Clarmar site have been evaluated and are being adjusted with feedback from FPS and the site owner. The three new elementary buildings are scheduled to be completed in Summer 2024.

 

Milliken Park Elementary Project Update: 

Bids were received and approved in May 2022. The project was within the established budget. A Notice of Award has been issued to Cheever Construction. The contract with Cheever Construction is being prepared.  Construction is expected to start in July 2022 and extend through December 2023 over multiple phases.

 

Lenihan Learning Center Project Update: 

Construction Documents are complete. The project is out to bid. Bids are due June 30th, with anticipated Board approval on July 11th. Construction is expected to begin in August 2022 and extend into next year, 2023.

 

Bell Field Elementary Project Update: 

The roof repair package bids were received on April 28. The Contract with Elkhorn West Construction is being prepared. Construction on the roof repair project will begin in June or July 2022. Scope and budget verification work is in progress in preparation for the interior design work to begin in the fall/winter of 2022-23 for bidding in the spring of 2023. Interior construction is scheduled to begin in the summer of 2023.

 

Linden Elementary Project Update: 

Site Survey work has been completed. Design work is scheduled to begin in July 2022.

 

Johnson Crossing Academic Center Project Update: 

Site Survey work has been completed. Design work is scheduled to begin in July 2022.

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1eiKo8P3XKxMAn857wcJO38PbQuc7oB_I/view?usp=sharing 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.

Fremont Public Schools Bond Issue 

Bond Issue Update

 

Fremont, Neb. – (May 16, 2022)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School / CTE Project Update:

Continued analysis of the costs for the project are being reviewed by the design team, contractor, and the school district to determine the final scope elements of the projects.  Geotechnical services have started this month on-site and the geothermal well field is currently out to bid with this work anticipated to begin this summer. The design and coordination work is continuing and the development of the structural, mechanical, electrical and plumbing systems will continue through October when the final design is scheduled to be completed.

 

Washington, Howard, and Clarmar Elementary Project Update:

Design and coordination of structural, mechanical, electrical, plumbing and architectural systems are ongoing. Detail design work on the interior finishes, casework and kitchen area is underway. Development of options for the new Clarmar site have been evaluated and it is being adjusted with feedback from FPS and the site owner. 

 

Milliken Park Elementary Project Update: 

Construction documents have been completed and include the final design, details and building systems for general contractor bidding. Bids will be received on May 19. Construction is expected to start in summer 2022 and extend through December 2023 over multiple phases.

 

Lenihan Learning Center Project Update: 

Construction documents are proceeding toward final completion on June 1. Bidding will be completed in June, with construction expected to start this summer 2022, and extend into next year, 2023.

 

Bell Field Elementary Project Update: 

The roof repair package bids were received on April 28 and are currently under review. Scope and budget verification work is in progress in preparation for the interior design work to begin in the fall/winter of 2022-23 for bidding in the spring of 2023. Interior construction is scheduled to begin in the summer of 2023.

 

Linden Elementary Project Update: 

Site survey work is in progress. Design work is scheduled to begin in July 2022.

 

Johnson Crossing Academic Center Project Update: 

Site survey work has been completed. Design work is scheduled to begin in July 2022.

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1DvcvpK_opGNVtWjDGPHLxX_JJ3ODaQ5u/view?usp=sharing 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.

Fremont Public Schools Bond Issue 

Bond Issue Update

Fremont, Neb. – (Apr. 20, 2022)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School / CTE Project Update: 

The High School Renovation and CTE project schematic design has been completed and Hausmann Construction has compiled an initial pricing estimate of the costs and schedule for the various parts of the proposed project based on that submittal.  The design team and Hausmann are going through a deep analysis of the pricing of the initial design elements.  Also, requests for proposals for geotechnical services were received and TD2 has been selected to provide those required services starting this month. The design work is on schedule and will continue through October with the early site/geothermal construction work beginning after school is out.

 

Washington, Howard, and Clarmar Elementary Project Update: 

Design and coordination of structural, mechanical, electrical and plumbing and architectural systems is ongoing. Detail design work on casework and interior finishes is underway. Development of options for the new elementary site have been evaluated and it is being adjusted with feedback from FPS and the site owner. 

 

Milliken Park Elementary Project Update: 

Construction documents have been completed and include the final design, details, and building systems for general contractor bidding. Bids are requested to be delivered on May 5th.   Construction is expected to start in Summer 2022 and extend through next year, 2023 over multiple phases.

 

Lenihan Learning Center Project Update: 

Design development document package has been completed.  Refinement of scope, details, and building systems will continue through the finalization of the construction documents in May.  Bidding will be completed in June, with construction expected to start this summer and extend into next year, 2023.

 

Bell Field Elementary Project Update: 

The roof repair package is out to bid with bids requested by April 28. Program, scope, and budget verification work is in progress in preparation for design work to begin for the interior work in the Spring of 2022.

 

Linden Elementary Project Update: 

Site Survey proposal requests will be issued in April in preparation for the design work which is scheduled to begin in the Summer of 2022.

 

Johnson Crossing Academic Center Project Update: 

Site Survey work has been completed. Design work is scheduled to begin in the Summer of 2022.

 

Bond Funding Update:

Fremont Public Schools working with DA Davidson issued $92 million of the $123 million the voters approved last September on March 17.  Due to the favorable bond market and the confirmation of the District’s A+ bond rating the bonds were sold at a 3.31% interest rate.  The bond proceeds were forwarded to the school district on March 31.  The remaining bonds will be sold at a later date.

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1y-HNQDqKOGhRgAAcoEzLzt2Lqpi69SOW/view?usp=sharing

Fremont Public Schools Bond Issue 

Bond Issue Update

 

Fremont, Neb. – (Mar. 24, 2022)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School / CTE Project Update:

The schematic design submittals for both the High School Renovation and CTE project has been completed and Hausmann Construction is currently pulling together initial pricing estimate costs for the proposed work. The initial test wells for the proposed geothermal system have been drilled at the High School campus and are currently being analyzed.  Also, a request for proposals for geotechnical services has been sent out with that work anticipated to start late March/Early April.   Meetings and discussions with staff will continue to take place during the design development phase through June. The design work is on schedule and will continue through October with the early site construction beginning once school is out in May 2022.

 

Washington, Howard, and Clarmar Elementary Project Update:

Design and coordination of structural, mechanical, electrical and plumbing and architectural systems is ongoing. Further work under development is occurring related to the exterior design and key interior spaces such as commons and the media center. Development of options for the new Clarmar site have been evaluated and it is being adjusted with feedback from FPS and the site owner. 

 

Milliken Park Elementary Project Update:

The Design Development document package has been completed with input from FPS representatives, and the next round of budget confirmation is currently in process. The initial test wells for the proposed geothermal system have been drilled at Milliken Park and are currently being analyzed. Refinement of scope, details, and building systems continues through finalization of the Construction Document package. Design work will continue in preparation for bidding in the Spring of 2022. 

 

Lenihan Learning Center Project Update:

Design Development document package is being finalized along with budget and scope confirmation.  Refinement of scope, details, and building systems will continue through finalization of the Construction Document package. Design work will continue in preparation for bidding in the Spring 2022.

 

Bell Field Elementary Project Update:

The Design Team and FPS are working on a bid package to repair roof areas that have been leaking. The roof repair package will go out to bid this spring. Program, scope and budget verification work is in progress in preparation for design work to begin for the interior work in the Spring 2022.

 

Linden Elementary Project Update:

Site Survey proposal requests will be issued in March in preparation for the design work which is scheduled to begin in Spring/Summer 2022.

 

Johnson Crossing Academic Center Project Update:

Site Survey work has been completed. Design work is scheduled to begin in Spring/Summer 2022.

 

Bond Funding Update:

Fremont Public Schools working with DA Davidson issued $92 million of the $123 million the voters approved last September on March 17.  Due to the favorable bond market and the confirmation of the District’s A+ bond rating the bonds were sold at a 3.31% interest rate.  The bond proceeds will be forwarded to the school district on March 31.  The remaining bonds will be sold at a later date.

 

“We continue to move forward with our bond planning process. We are excited to begin work this summer when school is out,” stated superintendent Mark Shepard. “Taking advantage of the favorable bond market was key in being able to accomplish the projects outlined when the voters gave their approval last fall,” Shepard concluded..

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1YYVG_EDOmFq62eAhMmNDnbKWk43PNfy0/view?usp=sharing 

 

###