To view the April 2024 Bond Project Update, please click on the following link:

https://drive.google.com/file/d/1nxGXDFZgRnMALhR6QK_B8mi_ML-9t3n9/view?usp=drive_link

To see the presentation presented at the June 12 Board of Education Meeting, click on the following link:

https://drive.google.com/file/d/1OYtHb7-o49Paq0–LJr2ZRGJa7KqUf8k/view?usp=drive_link

Fremont Public Schools Bond Issue 

Bond Issue Update

 

Fremont, Neb. – (Apr. 21, 2023)  The Design work and Bidding of all projects has been completed. The Design Team is meeting with the School District Administrative Team on an as-needed basis, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. OAC (Owner-Architect-Contractor) Meetings are held at each project site bi-monthly.

 

High School / CTE Project Update:

CTE site setup/demo is in progress. Footings and underground rough-ins are underway. Phase 1 of the project in area D & E is proceeding nicely and on track to be completed on schedule. Phase 2 rough-ins are near completion. 

 

Washington, Howard, and Clarmar Elementary Project Update: 

Steel, CMU, and exterior enclosure work is in progress at Howard Elementary. Underground utilities, foundations and masonry block walls are underway at Washington Elementary. Geothermal well field work is in the planning phases. Deer Pointe Elementary site work is ongoing.

 

Milliken Park Elementary Project Update:

Construction at Phase 1 and 3 classrooms and new administration is complete and the areas are now occupied.  Phase 2 construction at the east classroom pod is nearing completion with final install of finishes and city inspections.  Upon completion, Cheever Construction is planning to progress into phase 4 areas, i.e. locker rooms, existing administrative offices, and the music room.  Once students leave for summer break, phase 5 work in the commons, gymnasium and special education classrooms will commence.  Substantial completion is targeted for September 2023.

 

Lenihan Learning Center Project Update:

The new fluid cooler and platform structure has been set in place, and DR Anderson will be scheduling start up procedures with the mechanical contractor soon.  Rough-ins for new mechanical, electrical, and hydronic piping are complete, and all new window frames have been installed.  In the shop area of the building, removal and infill of the existing skylights is in process along with replacement of roof membrane and board insulation.   New light fixtures and ceiling grid materials are being installed.  Second floor is receiving new paint on the walls.  Construction is expected to be complete in July of 2023.

 

Bell Field Elementary Project Update: 

Bids were received on January 26th, 2023 and were presented to the BOE for approval on February 13th 2023. The bid submitted by Cheever Construction was approved. Project planning and scheduling is in progress. The  Interior construction is scheduled to begin in May-June of 2023. Construction is expected to be complete in August of 2024.

 

Linden Elementary Project Update: 

Bids were received on March 30th, 2023 and were presented to the BOE for approval on April 10th, 2023. The bid submitted by Cheever Construction was approved. A Pre-Construction meeting will be held in April. Construction is scheduled to begin in May-June of 2023. Construction is expected to be complete in August of 2024.

 

Johnson Crossing Academic Center Project Update: 

Bids were received on March 23rd, 2023 and were presented to the BOE for approval on April 10th, 2023. The bid submitted by Scheele-Kayton Construction was approved. A Pre-Construction meeting will be held in April. Construction is scheduled to begin in May-June of 2023. Construction is expected to be complete in August of 2024.

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1w0qPRwqjK94Au57zlUMrqXahV3JRly8S/view?usp=share_link 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.

Fremont Public Schools Bond Issue 

Bond Issue Update

 

Fremont, Neb. – (Mar. 31, 2023)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team and contractors weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School / CTE Project Update: 

Site construction for the new football field and track replacement is still underway.  The main site fencing for the CTE addition has been installed and construction has commenced. Overall project completion is slated to finish Summer of 2024.

 

Washington, Howard, and Clarmar Elementary Project Update: 

Steel and CMU work is in progress at Howard Elementary with several wings and gymnasium out of the ground. Steel and CMU work is in progress at Washington Elementary with the first wing and gymnasium out of the ground. Geothermal well field work is in the planning phases. Deer Pointe Elementary site work has commenced. 

 

Milliken Park Elementary Project Update:

Construction at Phase 1 Classrooms and Administration is complete and the area is now occupied.  Phase 2 construction at the East Classroom ‘pod’ is now in process and will continue through mid-April. Cheever Construction continues to coordinate site operations with the school and district administration. Construction will continue over several more future phases allowing the building to remain occupied, and is expected to be complete in December 2023.

 

Lenihan Learning Center Project Update:

The new fluid cooler and platform structure has been set in place.  Rough-ins for new mechanical and electrical are in process, including hydronic piping.  Fire sprinkler piping is in production.  Window frames installation is almost complete.  Construction is expected to be complete in July 2023.

 

Bell Field Elementary Project Update: 

The Phase 2 Interior design work was completed in December 2022. The Interior construction is scheduled to begin in May-June of 2023.

 

Linden Elementary Project Update: 

Bids were received on March 31, 2023. Construction is scheduled to begin in May-June of 2023.

 

Johnson Crossing Academic Center Project Update: 

Bids were received on March 23, 2023. Construction is scheduled to begin in May-June of 2023.

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1dtXiIIjBq2u2z6xQqN-VqHijOiPTxVnU/view?usp=sharing 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.

Fremont Public Schools Bond Issue 

Bond Issue Update

 

Fremont, Neb. – (Feb. 24, 2023)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team and contractors weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School / CTE Project Update: 

The final GMP (Guaranteed Maximum Price) has been agreed upon by the district and Hausmann Construction and was presented to the Board of Education at the February 13th meeting and approved.  Site construction for the new football field and track replacement is still underway.  The main site fencing for the CTE addition has been installed. Overall project completion is slated to finish Spring/Summer of 2024.

 

Washington, Howard, and Clarmar Elementary Project Update: 

Steel and CMU work is in progress at Howard Elementary with the first wing and gymnasium out of the ground. Underground utilities are underway at Washington Elementary as weather permits, foundations are to follow. Geothermal well field work is in the planning phases. Deer Pointe Elementary site work is substantially bid and construction planning ongoing with the City and Developer. 

 

Milliken Park Elementary Project Update:

Construction at Phase 1 Classrooms and Administration is complete and the area is now occupied.  Phase 2 construction at the East Classroom ‘pod’ is now in process and will continue through mid-April. Installation of new lighting at North Classrooms was completed during the winter holiday break. Cheever Construction continues to coordinate site operations with the school and district administration. Construction will continue over several more future phases allowing the building to remain occupied, and is expected to be complete in December 2023.

 

Lenihan Learning Center Project Update:

Demolition work is complete and the new fluid cooler and platform structure has been set in place.  Rough-ins for new mechanical and electrical are in process, including hydronic piping.  Fire sprinkler piping is in production.  Window frames have been received on site and have begun installation.  Construction is expected to be complete in July 2023.

 

Bell Field Elementary Project Update: 

The Phase 2 Interior design work was completed in December 2022. Bids were received on January 26th, 2023 and were approved by the Board on February 13th. The Interior construction is scheduled to begin in May-June of 2023.

 

Linden Elementary Project Update: 

The Design work is nearly complete and will go out to bid in February 2023. Bids will be received in March 2023. Construction is scheduled to begin in May-June of 2023.

 

Johnson Crossing Academic Center Project Update: 

The Design work is nearly complete and will go out to bid in February 2023. Bids will be received in March 2023. Construction is scheduled to begin in May-June of 2023.

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1KMuDxvfkCfDiPkp7mTJ-cS7K8FJGch4d/view?usp=share_link 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.

Fremont Public Schools Bond Issue 

Bond Issue Update

 

Fremont, Neb. – (Dec. 19, 2022)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School / CTE Project Update:

The final construction drawings were completed in November. The final bidding for the project has been completed – Hausmann Construction is working on the project GMP for discussion and approval in January.

 

Washington, Howard, and Clarmar Elementary Project Update: 

Grading, foundation and plumbing rough-in work is in progress at Howard Elementary. Grading and fill is underway at Washington Elementary –  foundations to follow. Site planning at Deer Pointe development is ongoing with City coordination happening for final platting. Site Package bidding package expected in the first part of next year. 

 

Milliken Park Elementary Project Update: 

The interior build-out of the Phase 1 Classrooms and Administration on the west wing is nearing completion. Cabinets, ceilings, lighting, and painting is in progress. Substantial Completion, and the associated design team punchlist for Phase 1, is scheduled for December 20th, 2022. The move from Phase 1 to Phase 2 is being coordinated with FPS Facilities and will take place over the Holiday break.  Construction will extend through December 2023 over multiple phases allowing use of the building during construction.

 

Lenihan Learning Center Project Update: 

Demolition work is nearing completion. Cutting floors and trenching for new underfloor utilities is in progress. Installation of new ductwork and hydronic piping is in progress.  Construction is expected to be complete in July of 2023.

 

Bell Field Elementary Project Update: 

Design work for the Phase 2 interior work will wrap in in December. The project will go out to bid immediately after the holidays, with bids received at the end of January 2023. Interior construction is scheduled to begin in May-June of 2023.

 

Linden Elementary Project Update: 

Design work is in progress in anticipation of Bidding in February-March of 2023. Construction is scheduled to begin in May-June of 2023.

 

Johnson Crossing Academic Center Project Update: 

Design work is in progress in anticipation of Bidding in February-March of 2023. Construction is scheduled to begin in May-June of 2023.

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1duT0t7-8F63gQnfXWk35oVhtHwTkAPOT/view?usp=share_link 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.