Fremont, Neb. – (Aug. 16, 2022)  Fremont Public Schools continues to move forward with plans for the $123 million bond issue that was passed by citizens in September 2021. FPS meets with the BVH Design Team weekly, updating the Board of Education monthly, and updating the Board of Education Facilities Committee monthly. 

 

High School/CTE Project Update:

The geothermal wellfield installation work is currently underway at the High School and is scheduled to continue through fall of this year. The Al Bahe gym bleacher replacement has an anticipated replacement timeframe of Spring 2023. An early site package for various exterior improvements will be submitted to Hausmann Construction for bidding at the end of August.  The project team will also be reviewing the updated estimate this month to confirm the anticipated overall project scope and costs for the High School and CTE Facility. The design team will continue to develop the drawings through October when final construction documents will be completed and initial exterior site construction is scheduled to commence.

 

Washington, Howard, and Clarmar Elementary Project Update: 

Construction documents are completed and planning to go to bid mid August with a bid date of September 1st. Interested bidders have been contacted. A pre-bid meeting is scheduled for August 17th followed up with a site walk of Washington and Howard to familiarize the bidders with the two sites. 

 

Milliken Park Elementary Project Update: 

Phase 1 Construction is underway. The geothermal well field has been completed. Cheever Construction has created temporary walls at the interior to separate the phase 1 work areas from the rest of the building. The demolition of the existing Classrooms in the phase 1 area has been completed. Interior trenching to accommodate Mechanical and Electrical work for phase 1 have been completed. Construction will extend through December 2023 over multiple phases allowing use of the building during construction.

 

Lenihan Learning Center Project Update: 

The project was bid on July 22nd. A contract with DR Anderson Constructors was approved by the Board of Education on July 26th. A pre-construction meeting was held on-site on August 4th. Ths contractor is proceeding with the construction of temporary classroom space in the Main Street – East Meeting Room. Construction within the Lenihan building will begin in August. The overall project is expected to be complete in July 2023.

 

Bell Field Elementary Project Update: 

Elkhorn West Construction has started work on the Phase 1 roof repair project which will be completed in August 2022. Scope and budget verification work is underway in preparation for the Phase 2 interior work. Design work for the Phase 2 interior work will take place during the fall of 2022 for Bidding in December 2022 or January 2023. Interior construction is scheduled to begin in May-June of 2023.

 

Linden Elementary Project Update: 

Scope, and Budget verification work is underway. Design work is starting in August 2022 in anticipation of Bidding in January-February of 2023. Construction is scheduled to begin in May-June of 2023.

 

Johnson Crossing Academic Center Project Update: 

Scope and budget verification work is underway. Design work is starting in August 2022 in anticipation of Bidding in January-February of 2023. Construction is scheduled to begin in May-June of 2023.

 

The projects continue to develop,” stated Dr. Brad Dahl, associate superintendent. “The volatility in the construction market continues to be a challenge for our team as plans are developed, priced out and ultimately bid.”

 

To view the presentation given at the Board of Education meeting, with preliminary designs, click here: https://drive.google.com/file/d/1AJzPy64Ry98BGRVZDJE2zCRKpPjrpg7V/view?usp=sharing 

 

###

The mission statement of the Fremont Public Schools is to produce creative, adaptable, productive citizens committed to lifelong learning.